The Township of Springwater is responsible for acquiring, maintaining and rehabilitating its infrastructure and assets to ensure that reliable service is provided to businesses and residents. Major infrastructure in the Township consists of roads, bridges and culverts, sewers, watermains and pumping stations, and facilities including recreation centres, libraries, parks, pavilions, fire stations and an administration centre.
Capital projects are prioritized by need and outlined in the Township's Ten Year Capital Plan. The summaries below provide information on recent and ongoing projects.
Road Construction & Infrastructure Replacement
Buckley Street (Gearin Street to Flos Road 4 West) |
This project will rehabilitate roads, watermains, sewers, and sidewalks throughout the Township.
Improvements include: New watermain, concrete and road rehabilitation
Project Start Date: May 1, 2023 Project End Date: August 31, 2023 Contract: Georgian Paving LTD |
Nursery Road (2.4 km south of Horseshoe Valley) |
This project will rehabilitate roads, watermains, sewers, and sidewalks throughout the Township.
Improvements include: Road rehabilitation & shoulder work
Project Start Date: May 1, 2023 Project End Date: August 31, 2023 Contract: Georgian Paving LTD |
Dobson Road (0.4 km south of Sunnidale Road) |
This project will rehabilitate roads, watermains, sewers, and sidewalks throughout the Township.
Improvements include: Road rehabilitation & shoulder work
Project Start Date: May 1, 2023 Project End Date: August 31, 2023 Contract: Georgian Paving LTD |
Flos Road 8 East (1.1 km east of County Road 27) |
This project will rehabilitate roads, watermains, sewers, and sidewalks throughout the Township. Improvements include: Road rehabilitation & shoulder work
Project Start Date: May 1, 2023 Project End Date: August 31, 2023 |
Bertram Drive, Archer Crescent, Nash Avenue |
This project will resurface various roads throughout the Township. Improvements include: Remove existing asphalt pavement and granulars, new road base granulars and new asphalt and match into existing driveways, new concrete sidewalk and tactile plates at intersections, new curb and gutter
Project Start Date: May 2023 Project End Date: November 2023 |
Wilson Drive (North of Hwy 26 to 1.35 kms north - refer to map) |
This project will resurface various roads throughout the Township. Improvements include: Remove existing asphalt pavement and granulars, new road base granulars and new asphalt and match into existing driveways, new granular shoulders along the roadway
Project Start Date: May 2023 Project End Date: November 2023 |
Flos Road 4 (East of Atkinson Road to the intersection of Riverdale Road - refer to map) |
This project will resurface various roads throughout the Township. Improvements include: Remove existing asphalt pavement and granulars, new road base granulars and new asphalt and match into existing driveways, new granular shoulders along the roadway
Project Start Date: May 2023 Project End Date: November 2023 |
Houden Street and Simcoe Street (From Yonge Street South to Queen Street East - refer to map) |
This project will resurface various roads throughout the Township. Improvements include: Remove existing asphalt pavement and granulars, install new 150 mm diameter watermain including new services to property line, new sidewalk including tactile plates, new road base granulars and new asphalt and match into existing driveways, restoration including new topsoil and sod
Project Start Date: May 2023 Project End Date: November 2023 |
Golf Course Road (Hendrie Road to Hwy 26) |
This project will resurface various roads throughout the Township. Improvements include: Remove existing asphalt pavement and granulars, new road base granulars and new asphalt and match into existing driveways, new road shoulders with granulars
Project Start Date: May 2023 Project End Date: November 2023 |
Craig Road Extension | ||||||||||
Description: The project involves the design and construction of the future Craig Road in Midhurst. Craig Road will be a two-lane roadway approximately 2.6 km in length, providing an east-west link between County Road 27 and the Russell Road/Forbes Road intersection. Project Status: The project is currently in the design phase. Contract Services:
Background: In 2009, the Township completed a Master Plan for the provisions of water, wastewater and transportation upgrades to accommodate future growth in the Midhurst area. The Craig Road extension was recommended under the Plan to carry traffic east and west to the north of the development rather than through Midhurst. In 2022, Ainley & Associates was retained to carry out the design and contract administration for the project. As per recommendations included in the 2020 Environmental Study Report, the project is moving forward in tandem with the first phase of Neighbourhood 2 of the Midhurst Secondary Plan. Project Manager: Mahesh Ramdeo - General Manager, Infrastructure & Operational Services 705-728-4784 x2051 |
Water/Wastewater
Swaley Drain Improvements | ||||||||||
Description: The project, under section 78 of the Drainage Act, is to improve and extend the outlet of the Swaley Drain. Project Status: Extension works are complete. Contract Services:
Background: In 2016, Springwater Council accepted a Notice of Drain Improvement from an affected land owner to improve the outlet of the Swaley Drain. The work was requested to alleviate current drainage issues, as field tile outlets are malfunctioning due to high and rising water levels within the drain. K. Smart and Associates was retained in 2017 to complete a Scoping Study, and in 2018 to prepare a Preliminary Report on the outlet of the Swaley Drain under Section 78 of the Drainage Act. In 2021, Council authorized a Final Report by Mr. Smart and provisionally passed Swaley Drain By-Law 2021-091 to approve the Final Report. As per Section 46 of the Drainage Act, Council held a Court of Revision on November 1, 2021 to hear landowner challenges to their assessments within the provisionally adopted Swaley Drain By-Law. Extension works commenced in January 2022 and were completed by Dan Higgs Excavating & Marine Services. Project Manager: Steve Buchanan - Operations Technician 705-728-4784 x2075 |
Elmvale Lift Station | ||||||
Description: The project is to construct a new sewage lift station at 105 Queen Street West in Elmvale. The facility will replace the existing lift station at 99 Queen Street West. Project Status: Construction is complete. Contract Services:
Background: In 2014, the Township completed an assessment of the existing facility and confirmed that it was operating at 94% of its maximum capacity. An expansion to the facility was deemed necessary to accommodate existing operational demands and future growth in the area. Ainley Group was retained in 2017 to carry out the design and contract administration for the project. After the first contractor defaulted, the construction of the new station was retendered to Jeviso Construction Corporation in 2020. Project Manager: John Mabira - Senior Project Engineer 705-728-4784 x2071 |
Recreational & Community Facilities
Community Hub & Fire Station 2 | ||||||||
Description: The project is to construct a Community Hub at the recently acquired 1132 Snow Valley Road (Hasty Tract) property in Midhurst. Proposed municipal services for the property include, but are not limited to, a new fire station and fire service training area, County of Simcoe Emergency Medical Services (EMS) post, recreation complex, library and creative space, meeting and activity space, and active and passive recreation areas. Project Status: Phase 1 and Phase 2 development of the project are moving forward in tandem. Contract Services:
Background: In November 2020, Council approved the purchase of a 50-acre parcel of land from the Ministry of Natural Resources and Forestry at a cost of $3,884,846 plus HST for the establishment of a community hub. Phase 1 development of the Community Hub project was approved by Council in April 2021, with Ainley Group retained for project management. Phase 1 includes site preparation (studies/survey, tree clearing and civil works) as well as the construction of a new Fire Station 2 and potential Simcoe County EMS post. In December 2021, Masri O Inc. was awarded the contract for Phase 1 design works of the new fire station. The preliminary design was approved by Council in June 2022 and staff were directed to move forward with issuing a tender for the ultimate construction of the facility. On September 15, 2021, Council approved moving forward with Phase 2 of the project. An RFP was issued and awarded to Weston Consulting for the preparation of a Community Hub Master Plan. As part of the master planning process, the consultant is responsible for public consultation, preparing a long-term concept plan for the property, site servicing, cost projections and design criteria for future facility development. Project Manager: Mahesh Ramdeo - General Manager, Infrastructure & Operational Services 705-728-4784 x2051 |
County of Simcoe Projects
The County of Simcoe is responsible for the operation, construction and maintenance of the County transportation and bridge network, which is an infrastructure of roads, bridges, culverts and signalized intersections. To learn more about capital projects occurring at the County level, visit the Transportation and Engineering page on the County's website.
County projects that are ongoing in the Township of Springwater include:
- County Road 53 Roundabout Project (Wilson/Seadon/Carson intersection)
- Wye River South Bridge - EA / Design
- Concession 8/9, Lot 8 Culvert - Design / Property
- CR 22 - ERRC - Intersection Improvements - Engineering / Design
- Matheson Creek Bridge - Property / Site Prep / Utilities
- Willow Creek Bridge - EA / Design
- Vigo Bridge Settlement Monitoring
- County Road 29 Microsurfacing
- County Road 53 Microsurfacing
- Willow Creek Bridges - 4 Structures EA / Design
Contact Us