At the Council Meeting on December 7, 2016, Council accepted a Notice of Drain Improvement from an affected land owner to improve the outlet of the Swaley Drain. This work was requested to alleviate current drainage issues as field tile outlets are malfunctioning due to high and rising water levels within the drain.
In 2017, Kenn Smart of K. Smart and Associates was appointed to complete a Scoping Study involving affiliated and affected parties of the Swaley Drain. Mr. Smart was then appointed to prepare a Preliminary Report on the outlet of the Swaley Drain under Section 78 of the Drainage Act.
In 2021, Council authorized a Final Report by Mr. Smart and provisionally passed Swaley Drain By-Law 2021-091 to approve the Final Report. As per Section 46 of the Drainage Act, a Court of Revision was held on November 1, 2021 to hear landowner challenges to their assessments within the provisionally adopted Swaley Drain By-Law.
Extension works commenced in January 2022 and concluded in February 2022. The total estimated project cost is $357,000.00.
Related Studies and Staff Reports
Swaley Drain Status Update - 2022-02-22
Report - Swaley Drain Update 2021-04-21
Appendix A - Drain Improvement Procedure Updated Status
Presentation to Council - 2020-05-20
Report - Swaley Drain Update - 2019-09-04
Report - Swaley Drain Update - 2018-08-01
Report - Swaley Drain Scoping Study and Appointment of Drainage Engineer - 2018-04-18
Scoping Study 16-387 - report Mar 2018
Scoping Study 16-387 Appendix 1
Report - Swaley Drain Update - 2017-02-15
Report - Swaley Drain Notice for Drain Improvement - 2016-12-07